Dear all,
We attended the meeting with FH & Conlay Construction on 14MAR2013 and append below are the updates.
Attached progress report for your perusal. FH_14MAR2013
Latest photo @ site:
1) Completion rate is 68.82% which is ahead of schedule rate of 68.02 as at 11MAR2013.
2) Currently there is 208 workers on site working 7 days week to meet the construction deadline.
3) Internal flooring has been completed for Block B while progressing till 8th floor for Block A
4) Lift has been installed for both blocks with test on low speed, once TNB certification complete high speed test will be conduct.
5) Part of the painting work will be done for Block B (subject to weather permitted) while painting for Block A will be done once the exterior plastering work is complete.
6) Master title has been redeemed, pending release from Maybank. FH committed to submit for Strata Title application within 6 – 12 months on VP delivery. Target to receive CF in 2 months time from submission to local council, KPKT is in the loop on the progress of construction and subsequently application for CF, VP & Strata Title.
7) FH has received permit to sell the terminated units and target to begin the selling progress by early APR2013, showroom will be construct to attract buyer. Indicative selling price of MYR 220K onwards. Please contact FH if interested to purchase.
Next meeting will be held in May prior to completion of the construction.
Cheers,
Vincent